• Elementary Schools

    Caleb's Creek (New)

    Moore Replacement

    Ibraham Replacement

    Kimmel Farm (New)

    Morgan Elementary (Clemmons Area (New)

    Old Richmond (Demolition)

    Sedge Garden Addition

    Diggs Replacement

    Piney Grove HVAC

    Vienna HVAC 

    Sherwood Forest Addition and Partial Renovation 

    Speas Renovation 

    Zone 1-Kernersville Area (New)

     
     
     
     
     


     

    Caleb's Creek Elementary School- Project Completed. New 95,000 sq. ft. elementary school located in Kernersville, North Carolina designed for 800 students and support spaces.
    Address: 1109 Salem Crossing Road, Kernersville, NC  27284

    Opening Date: August, 2009  

    Bid Date: January 8, 2008  

    Contractor: Lyon Construction Co.  (336) 983-3000

    Contract Amount: $11,398,000.00

    Architect:  Peterson/Gordon Architects - (336) 760-1411

     
    Moore Elementary School Replacement- Project Completed. Construction of new 77,000 sq. ft. elementary school on the present site for 600 students and support spaces. 

    Click here for a rendering of Moore's new building .

    Opening Date: Building-Revised: Nov 2009;  Site-Revised: Fall 2010

    Bid Date:    April 3, 2008

    Contractor:   Triad Builders of King (336) 983-5126

    Contract Amount: $9,278,800.00

    Architect:  Ersoy Brake Appleyard Architects - (336) 725-1361

     
     

    Ibraham Elementary School Replacement- Project Completed. Construction of new 59,533 sq. ft. elementary school on the present site for 450 students and support spaces.  The existing 1998 addition will be saved and incorporated into the new construction.

    Opening Date:   April, 2009 Site:   Fall, 2009

    Bid Date:     October 11, 2007

    Contractor:   Lyon Construction Co. (336) 983-3000

    Contract Amount: $8,538,000.00

    Architect:  Thomas H. Hughes Architecture - (336) 722-4447

     
    Kimmel Farm Elementary School- Project Completed. New 80,000 sq. ft. elementary school located in Winston-Salem, North Carolina for 720 students and support spaces. Address: 4672 Ebert Road, Winston-Salem, NC  27127

    Opening Date: July, 2009

    Bid Date:     May 13, 2008

    Actual Bid Date:   May 13, 2008

    Contractor: Shelco, Inc. (336) 760-5055

    Contract Amount: $23,969,400.00 (Bid jointly with Flat Rock Middle)

    Architect:  Peterson/Gordon Architecture - (336) 760-1411



    Morgan Elementary  School (Clemmons Area)   -  Project Completed. 3210 Village Point Drive, Clemmons. New 96,505 sq. ft. elementary school located in Clemmons, North Carolina for 720 students and support spaces.

    Click here for a rendering of the new Zone 7 Elementary .

    Projected Opening Date: July, 2009   Revised: July, 2011

    Plans Available:  October 26, 2009

    Bid Date:  November 24, 2009

    Contractor: R.L. Casey Construction Company (336) 292-8227

    Contract Amount: $11,670,039.00

    Architect:  Walter Robbs Callahan & Pierce - (336) 725-1371

     
     
    Old Richmond Elementary School- Project Completed. Demolition of old classroom building.

    Date of Demolition: May 1, 2008

    Bid Date: December 18, 2007

    Contractor: EME, Inc.

    Contract Amount: $19,839.00  

    Architect:  Trinity Environmental, LLC - (336) 475-5163

       

    Rural Hall Elementary SchoolAddition- Project Completed. Addition of approximately 32,660 sq. ft. which will include replacement of the existing 1950's classroom wing.

    Opening Date:    Phased: Spring 2010 thru August, 2010

    Bid Date: January 8, 2009

    Contractor: Hendrick Construction (704) 887-0280

    Contract Amount: $5,039,843.00

    Architect:  Ersoy Brake Appleyard Architects - (336) 725-1371

     
     
     
    Sedge Garden Elementary SchoolAddition- Project Completed. Addition of approximately 33,000 sq. ft. which will include replacement of the existing 1950's classroom wings.

    Click here for a rendering of Sedge Garden's new building .

    Opening Date: Addition: Spring 2010  Site: Fall 2010

    Bid Date: March 10, 2009

    Contractor: R. P. Murray (336) 996-2000

    Contract Amount: $4,185,000.00

    Architect:  Thomas H. Hughes Architecture - (336) 722-4447

     
     
    Diggs Elementary School  Replacement- Project Completed. Replacement of existing school designed for 600 students and support spaces. Consolidation at Latham Elementary Site.

    Click here for a rendering of the new Diggs-Latham building .

    Opening Date: Phased Openings: July, 2010 - December 2010

    Bid Date: May 6, 2009

    Contractor: Shelco, Inc. (336) 760-5055

    Contract Amount: $7,195,000.00

    Architect: Calloway Johnson Moore & West - (336) 724-1503

     
     
     
    Piney Grove Elementary School HVAC- Project Completed. Install outside air units.

    Projected Opening Date:    Fall 2010

    Projected Plans Available:    Summer 2010

    Bid Date:    June 15, 2010

    Contractor:   Chapman Mechanical

    Contract Amount:   $879,000.00

    Architect:  CES Engineering (336) 725-0124

     
     
    Vienna Elementary School HVAC- Renovate Kitchen, Restrooms. Replace heat pumps and install outside air units in the 1950's buildings. 

    Projected Opening Date:   Phased HVAC Work Spring 2012 - December 2012

    Projected Plans Available:    November 2011
     
    Bid Date:    December 7, 2011

    Contractor: Wishon & Carter Builders

    Contract Amount: $3,464,927.00

    Architect:    Peterson/Gordon Architecture (336) 760-1411

    WS/FCS Construction Specialist:   Barry Motsinger

     
     
    Sherwood ForestElementary School Addition - Project Completed. Addition of approximately 18,000sq. ft. and renovation of approximately 6,500 sq. ft.

    Click here for a rendering of Sherwood Forest's renovations .

    Opening Date: Phased: December, 2009 thru Spring 2010

    Bid Date: February 24, 2009

    Contractor: Shelco, Inc. (336) 760-5055

    Contract Amount: $3,629,300.00

    Architect:  Jimmy L. Norwood, Jr. Architect - (336) 744-8100

     

    Speas Elementary SchoolPartial Renovation- Project Completed. Renovation of approximately 53,789 sq. ft. and an addition of approximately 15,259 sq. ft.

    Click here for a rendering of Speas' renovations .

    Projected Opening Date: Phased: Summer 2010 thru Fall 2011

    Bid Date: October 24, 2009

    Contractor: Farley Associates (803-547-5727)

    Contract Amount: $6,733,000

    Architect:  Thomas H. Hughes Architecture - (336) 722-4447

     

     
    Zone 1 Elementary School (Kernersville Area) - 4250 Johnny Knoll Lane, Winston-Salem. New 89,753 sq. ft elementary school for 720 students and support spaces.

    Projected Opening Date: July, 2012, Revised Fall 2013

    Projected Plans Available: February 2011

    Projected Bid Date: April 7, 2011

    Contractor: R K Stewart & Son Builders (336) 883-7111

    Contract Amount:   $11,768,000.00

    Architect:  Ersoy Brake Appleyard Architects - (336) 725-1361

    WS/FCS Construction Specialist:  Barry Motsinger